Maldives : Project Preparatory and Capacity Building for Renewable Energy Projects
The transaction technical assistance (TA) facility will support project preparation and renewable energy related capacity building in the Maldives. The TA will also provide support to ensure project sustainability and transfer capacity through specific training and skills-building activities as required. The TA will support preparatory work of the following projects:
(i)Preparation of Accelerating Sustainable System Development Using Renewable Energy II (ASSURE II) Project, and
(ii)Preliminary studies for Green Mobility Project.
Project Details
-
Project Officer
Kolantharaj, Jaimes
Sectors Group
Request for information -
Country/Economy
Maldives -
Sector
- Energy
Project Name | Project Preparatory and Capacity Building for Renewable Energy Projects | ||||
Project Number | 57208-001 | ||||
Country / Economy | Maldives |
||||
Project Status | Active | ||||
Project Type / Modality of Assistance | Technical Assistance |
||||
Source of Funding / Amount |
|
||||
Operational Priorities | OP1: Addressing remaining poverty and reducing inequalities OP2: Accelerating progress in gender equality OP3: Tackling climate change, building climate and disaster resilience, and enhancing environmental sustainability OP6: Strengthening governance and institutional capacity |
||||
Sector / Subsector | Energy / Energy efficiency and conservation |
||||
Gender | Effective gender mainstreaming | ||||
Description | The transaction technical assistance (TA) facility will support project preparation and renewable energy related capacity building in the Maldives. The TA will also provide support to ensure project sustainability and transfer capacity through specific training and skills-building activities as required. The TA will support preparatory work of the following projects: (i)Preparation of Accelerating Sustainable System Development Using Renewable Energy II (ASSURE II) Project, and (ii)Preliminary studies for Green Mobility Project. |
||||
Project Rationale and Linkage to Country/Regional Strategy | The Maldives is an archipelago composed of 1,192 small islands, with 187 inhabited, 79 leased for agricultural and/or industrial purposes, and 293 designated for tourism development . The country has a population of 515,122 people and heavily relies on tourism, contributing 26% to its GDP . Fossil fuel imports, mainly diesel fuel and LPG, meet the energy demands, accounting for about 8% to 10% of the country's GDP. The power sector consists of two utility companies operating multiple powerhouses. Diesel generation capacity of 320 MW is installed on inhabited islands, with 162 MW in the Greater Male' region and 210 MW on resort islands. Renewable energy capacity, primarily from solar PV systems, is around 53 MW, but power generation costs are high due to oversized systems and lack of power interconnection between islands. |
||||
Impact |
Project Outcome | |
---|---|
Description of Outcome | |
Progress Toward Outcome | |
Implementation Progress | |
Description of Project Outputs | |
Status of Implementation Progress (Outputs, Activities, and Issues) | |
Geographical Location | Nation-wide |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | |
Involuntary Resettlement | |
Indigenous Peoples | |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | |
During Project Implementation |
Responsible ADB Officer | Kolantharaj, Jaimes |
Responsible ADB Department | Sectors Group |
Responsible ADB Division | Energy Sector Office (SG-ENE) |
Executing Agencies |
Ministry of Finance (formerly Ministry of Finance and Treasury) |
Timetable | |
---|---|
Concept Clearance | - |
Fact Finding | - |
MRM | - |
Approval | 23 Nov 2023 |
Last Review Mission | - |
Last PDS Update | 28 Nov 2023 |
TA 10199-MLD
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
23 Nov 2023 | 12 Dec 2023 | 12 Dec 2023 | 30 Sep 2025 | - | - |
Financing Plan/TA Utilization | Cumulative Disbursements | |||||||
---|---|---|---|---|---|---|---|---|
ADB | Cofinancing | Counterpart | Total | Date | Amount | |||
Gov | Beneficiaries | Project Sponsor | Others | |||||
1,000,000.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 1,000,000.00 | 08 Jan 2024 | 0.00 |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Title | Document Type | Document Date |
---|---|---|
Project Preparatory and Capacity Building for Renewable Energy Projects: Technical Assistance Report | Technical Assistance Reports | Nov 2023 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
Tender Title | Type | Status | Posting Date | Deadline |
---|---|---|---|---|
Renewable Energy (Hybrid PV/Storage Minigrids) Expert | Individual - Consulting | Active |
Contracts Awarded
Procurement Plan
None currently available.