Indonesia : Accelerating Indonesia’s Clean Energy Transition Program – Phase 1

Sovereign Project | 56140-001

Project Details

Project Name Accelerating Indonesia’s Clean Energy Transition Program – Phase 1
Project Number 56140-001
Country / Economy Indonesia
Project Status Proposed
Project Type / Modality of Assistance Grant
Loan
Source of Funding / Amount
Loan: Accelerating Indonesias Clean Energy Transition Program " Phase 1
Ordinary capital resources US$ 470.00 million
Operational Priorities OP2: Accelerating progress in gender equality
OP3: Tackling climate change, building climate and disaster resilience, and enhancing environmental sustainability
OP6: Strengthening governance and institutional capacity
Sector / Subsector

Energy / Energy sector development and institutional reform

Gender Effective gender mainstreaming
Description
Project Rationale and Linkage to Country/Regional Strategy
Impact

Progressive, just, and prosperous Indonesia realized by 2045.

Outcome

Reliable and cleaner electricity supplied

Outputs

Transition to renewable clean electricity supply facilitated

Smart transmission grid infrastructure expanded

Institutional capacity to manage a just energy transition enhanced

Geographical Location Nation-wide, Bali, East Nusa Tenggara, Java, Sulawesi, Sumatra
Safeguard Categories
Environment B
Involuntary Resettlement A
Indigenous Peoples B
Summary of Environmental and Social Aspects
Environmental Aspects
Involuntary Resettlement
Indigenous Peoples
Stakeholder Communication, Participation, and Consultation
During Project Design
During Project Implementation
Responsible ADB Officer Schmidt, Daniela
Responsible ADB Department Sectors Group
Responsible ADB Division Energy Sector Office (SG-ENE)
Executing Agencies
P.T. Perusahaan Listrik Negara
Timetable
Concept Clearance 22 Sep 2022
Fact Finding 02 May 2023 to 05 May 2023
MRM -
Approval -
Last Review Mission -
Last PDS Update 07 Oct 2022

Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.

The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.

The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.

In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Title Document Type Document Date
Accelerating Indonesia’s Clean Energy Transition Program - Phase 1: Initial Poverty and Social Analysis Initial Poverty and Social Analysis Oct 2022

Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.

None currently available.


Evaluation Documents See also: Independent Evaluation

None currently available.


Related Publications

None currently available.


The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.

Requests for information may also be directed to the InfoUnit.

Tenders

No tenders for this project were found.

Contracts Awarded

No contracts awarded for this project were found

Procurement Plan

None currently available.