Tonga : Improving Economic Management Program, Subprogram 1
Project Details
-
Project Officer
Webb, James M.
Sectors Group
Request for information -
Country/Economy
Tonga -
Sector
- Public sector management
Project Name | Improving Economic Management Program, Subprogram 1 | ||||||||||
Project Number | 56358-001 | ||||||||||
Country / Economy | Tonga |
||||||||||
Project Status | Proposed | ||||||||||
Project Type / Modality of Assistance | Grant |
||||||||||
Source of Funding / Amount |
|
||||||||||
Operational Priorities | OP1: Addressing remaining poverty and reducing inequalities OP2: Accelerating progress in gender equality OP3: Tackling climate change, building climate and disaster resilience, and enhancing environmental sustainability OP6: Strengthening governance and institutional capacity OP7: Fostering regional cooperation and integration |
||||||||||
Sector / Subsector |
Industry and trade / Trade and services Public sector management / Public expenditure and fiscal management - Social protection initiatives |
||||||||||
Gender | Some gender elements | ||||||||||
Description | |||||||||||
Project Rationale and Linkage to Country/Regional Strategy | |||||||||||
Impact | |||||||||||
Outcome | |||||||||||
Outputs | |||||||||||
Geographical Location | Nation-wide |
Safeguard Categories | |
---|---|
Environment | C |
Involuntary Resettlement | C |
Indigenous Peoples | C |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | |
Involuntary Resettlement | |
Indigenous Peoples | |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | |
During Project Implementation |
Responsible ADB Officer | Webb, James M. |
Responsible ADB Department | Sectors Group |
Responsible ADB Division | Public Sector Management and Governance Sector Office (SG-PSMG) |
Executing Agencies |
Ministry of Finance |
Timetable | |
---|---|
Concept Clearance | 25 Aug 2023 |
Fact Finding | 25 Sep 2023 to 10 Nov 2023 |
MRM | - |
Approval | - |
Last Review Mission | - |
Last PDS Update | 01 Sep 2023 |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Title | Document Type | Document Date |
---|---|---|
Improving Economic Management Program, Subprogram 1: Concept Paper | Concept Papers | Aug 2023 |
Improving Economic Management Program, Subprogram 1: Initial Poverty and Social Analysis | Initial Poverty and Social Analysis | Jul 2023 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
Contracts Awarded
Procurement Plan
None currently available.