Vanuatu : Tropical Cyclone Lola Emergency Response Project
Project Details
-
Project Officer
Kim, Mary J.
Pacific Department
Request for information -
Country/Economy
Vanuatu -
Sector
- Public sector management
Project Name | Tropical Cyclone Lola Emergency Response Project | ||||
Project Number | 57318-001 | ||||
Country / Economy | Vanuatu |
||||
Project Status | Active | ||||
Project Type / Modality of Assistance | Grant |
||||
Source of Funding / Amount |
|
||||
Operational Priorities | OP6: Strengthening governance and institutional capacity |
||||
Sector / Subsector | Public sector management / Public expenditure and fiscal management |
||||
Gender | No gender elements | ||||
Description | |||||
Project Rationale and Linkage to Country/Regional Strategy | TC Lola has occurred during a period of disasters in close succession. Vanuatu's resources were already strained as previous disaster recovery efforts continue following the impacts of TC Judy, TC Kevin and the two earthquakes within a three-day period in March 2023. Responding to TC Lola is of a scale beyond the government's current capacity to restore life-sustaining services to the affected population in a reasonable time. There is a clear need to supplement government resources with additional support from development partners. | ||||
Impact |
Project Outcome | |
---|---|
Description of Outcome | To alleviate financial resource constraints to meet immediate needs and deliver disaster response where required. |
Progress Toward Outcome | |
Implementation Progress | |
Description of Project Outputs | Not relevant N/A |
Status of Implementation Progress (Outputs, Activities, and Issues) | |
Geographical Location | Nation-wide |
Safeguard Categories | |
---|---|
Environment | C |
Involuntary Resettlement | C |
Indigenous Peoples | C |
Summary of Environmental and Social Aspects | |
---|---|
Environmental Aspects | |
Involuntary Resettlement | |
Indigenous Peoples | |
Stakeholder Communication, Participation, and Consultation | |
During Project Design | |
During Project Implementation |
Responsible ADB Officer | Kim, Mary J. |
Responsible ADB Department | Pacific Department |
Responsible ADB Division | Pacific Liaison and Coordination Office in Sydney, Australia (PLCO) |
Executing Agencies |
Ministry of Finance & Economic Management |
Timetable | |
---|---|
Concept Clearance | - |
Fact Finding | 27 Nov 2023 to 27 Nov 2023 |
MRM | - |
Approval | 06 Dec 2023 |
Last Review Mission | - |
Last PDS Update | 06 Dec 2023 |
Grant 0923-VAN
Milestones | |||||
---|---|---|---|---|---|
Approval | Signing Date | Effectivity Date | Closing | ||
Original | Revised | Actual | |||
06 Dec 2023 | 12 Dec 2023 | 13 Dec 2023 | 12 Jun 2024 | - | - |
Financing Plan | Grant Utilization | ||||
---|---|---|---|---|---|
Total (Amount in US$ million) | Date | ADB | Others | Net Percentage | |
Project Cost | 0.50 | Cumulative Contract Awards | |||
ADB | 0.50 | 22 Dec 2023 | 0.00 | 0.00 | 0% |
Counterpart | 0.00 | Cumulative Disbursements | |||
Cofinancing | 0.00 | 22 Dec 2023 | 0.50 | 0.00 | 100% |
Project Data Sheets (PDS) contain summary information on the project or program. Because the PDS is a work in progress, some information may not be included in its initial version but will be added as it becomes available. Information about proposed projects is tentative and indicative.
The Access to Information Policy (AIP) recognizes that transparency and accountability are essential to development effectiveness. It establishes the disclosure requirements for documents and information ADB produces or requires to be produced.
The Accountability Mechanism provides a forum where people adversely affected by ADB-assisted projects can voice and seek solutions to their problems and report alleged noncompliance of ADB's operational policies and procedures.
In preparing any country program or strategy, financing any project, or by making any designation of, or reference to, a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.
Title | Document Type | Document Date |
---|---|---|
Grant Agreement (Asia Pacific Disaster Response Fund) for Grant 0923-VAN: Tropical Cyclone Lola Emergency Response Project | Grant Agreement | Dec 2023 |
Safeguard Documents See also: Safeguards
Safeguard documents provided at the time of project/facility approval may also be found in the list of linked documents provided with the Report and Recommendation of the President.
None currently available.
Evaluation Documents See also: Independent Evaluation
None currently available.
Related Publications
None currently available.
The Access to Information Policy (AIP) establishes the disclosure requirements for documents and information ADB produces or requires to be produced in its operations to facilitate stakeholder participation in ADB's decision-making. For more information, refer to the Safeguard Policy Statement, Operations Manual F1, and Operations Manual L3.
Requests for information may also be directed to the InfoUnit.
Tenders
Contracts Awarded
Procurement Plan
None currently available.